Construction Status

 

This week's current status on Hamilton:

  • Manson/Dutra Noise Notice to Residents (click to view document)

  • Hamilton
    3E contractor placing dredged material to Hamilton site. Work hours are 6:00 a.m. to 7:00 a.m. prep time and from 7:00 a.m. to 10:00 p.m. work time. No work on Sunday.
    South Levee construction work will start in the summer
    Water sampling on site ongoing
    Onsite construction security - 24 hours.

  • Hamilton Wetland Restoration Project (HWRP)
    N2, South Levee, and Intertidal Berm Contract - ongoing construction.

  • Oakland Harbor -50 Foot Deepening Project
    3E Contract - assembling of landside pipes, installation of electrical substation and power poles, and assembling of booster pumps
  • For your personal safety, please do not enter the active constructive zones on the Hamilton Wetlands Restoration project. Thank you for your cooperation and understanding.

Click on the map to zoom in.

 

  • Hamilton Wetland Restoration Project
    N2, South Levees, and Intertidal Berms contract is constructing levees and intertidal berms.

  • Oakland Harbor -50 Foot Deepening Project
    3E Contract is working on completing the installation of the electrical poles, substation, and power line for the Offloader to deliver dredged material from Oakland Harbor.

  • Point of Contact on site, Frank Smith 415-289-3323 and Captain Mark DeSantis 415-289-3303